Site works at emerging manganese miner Element 25’s Butcherbird Minesite will be commencing in December. ProjX has been assisting Element 25 with their maiden project since April this year and have completed the engineering design phase of the project. ProjX are planning the mobilising to site of their site construction management team, with the construction planned to be complete in Q1 2021.
ProjX Director David Teasdale:
“Our team of engineers and project personnel have done a great job working with the owner’s team to get E25’s project to this point. With a low capital budget and an aggressive schedule, this is where we work at our best. Processing equipment is procured, steel fabrication is well advanced, and civils and concrete works are planned to commence in December.”